Construction Updates From Concept to Reality We deliver what we promise Mall of Arabia Raft Foundation: 100% Completed Basement 1: 30% Completed Basement 2: 50% Completed Basement 3: 70% Completed Grey Structure Completion Date: Nov, 2022 Total Steel Consumption: 755 Tons Total Concrete Poured: 10500 Cubic Meter Covered Area: 1,410,064 sqft Florence Galleria Grey Structure Completed uptill: 9th Floor External Block Masonry: 58% Completed Grey Structure Completion Date: January, 2022 Total Steel Consumption: 1805 Tons Total Concrete Poured: 12773.7 Cubic Meter Covered Area: 264,347 sqft Courtyard by Marriott Raft Foundation: 100% Completed Basement 1: 8% Completed Basement 2: 70% Completed Excavation and Piling: 100% Completed Grey Structure Completion Date: August, 2022 Covered Area: 334,474 sqft IMARAT Builders Mall Tentative Completion Date: 1st January, 2022 Covered Area: 165,355 sqft